TCN fails to meet May 27 deadline over alleged vandals’ activities in N/E

Date:

Share post:

The Transmission Company of Nigeria,on Monday stated that tower number T290, one of the four new towers erected by its contractors along the Jos – Gombe 330kV transmission line collapsed during the cable stringing process.

According to TCN, the incident occurred at about 7am,  27th May, 2024, while the contractor was stringing the cable on the last tower, which was supposed to enable the final jointing of the power cable in time for energising of the line today.

This was contained in a press statement signed by Ndidi Mbah, General Manager Public Affairs, who company disclosed that despite  security challenges in the area, TCN contractors and some of its engineering staff worked tirelessly to fast-track the project, doing all that was humanly possible to meet the time-line. Daily, the contractor, TCN engineers accompanied by security operatives consistently left the site by 10pm in the night and resumed work at 6am every day.

Mbah said, “Constructing towers and stringing power cables at such heights is highly technical, although TCN contractors and staff have successfully completed similar projects in other parts of the country. The collapse of the fourth tower is a significant setback, given the extensive efforts to ensure that today’s power restoration timeline was met.

‘Our contractor is currently dismantling the collapsed tower members, to enable its reconstruction and final restringing of the cable. It is unfortunate to note that while TCN is working on reconstructing and restringing the four vandalised towers, three (3) towers along the Biu – Danbua 132kV transmission line were also vandalized with 16 spans of conductors stolen. The towers, which have all collapsed include towers T1690, T1691 and T1692. TCN has mobilized a contractor to commence their reconstruction. This discovery was made by TCN patrol team, last Friday.”

The statement noted that additionally, on Monday , the TCN lines patrol team discovered that tower T540 along the Makurdi – Jos 330kV double circuit transmission line has been vandalised. Sections of the tower have been removed, although the tower remains standing. TCN has contracted emergency repairs, to prevent its collapse.

“We reiterate our commitment to restoring normal bulk power supply through the distribution companies serving the North East and other areas affected by vandalism. There is however an urgent need for everyone to join hand with TCN in protecting our collective assets by being vigilant and reporting any suspected acts of tower and line vandalism promptly,” the statement added.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

spot_img

Related articles

Maiduguri Floods: Murderer who escaped from prison rearrested by Police

The Borno State Police Command has successfully re-arrested an escaped convict, Abubakar Mohammed, 27, who had been serving...

Borno Flood: NAF begins airlift of essential materials to victims

The Nigerian Air Force, NAF, has commenced airlift missions to transport relief materials to victims of flood disasters...

Omoyele Sowore confirms his release after arrest

Former presidential candidate of the African Action Congress, AAC, Omoyele Sowore, has confirmed his release after his arrest...

Over 40 people reported dead in a boat mishap in Zamfara community

No fewer than forty people were reported to have lost their lives in a boat mishap in Gummi...